Action Date | Action Description |
---|---|
Jul 26, 2023 | Assent Application Received |
Jul 31, 2023 | Administrative Review for Completeness |
Aug 02, 2023 | Bio Team Review for Completeness |
Aug 08, 2023 | Project Manager |
Aug 08, 2023 | Application Accepted |
Aug 08, 2023 | Eng Team Review for Completeness |
Aug 25, 2023 | HPHC Historical Preservation No Effect |
Sep 26, 2023 | 30 day Public Notice Issued |
Oct 26, 2023 | Public Notice End Date |
Nov 29, 2023 | Engineering Report |
Dec 05, 2023 | Typist for Processing |
Dec 05, 2023 | Executive Sign Off |
Dec 05, 2023 | Sent to Photo Copy |
Dec 05, 2023 | Permit Approved |
Dec 06, 2023 | Permit Mailed |
Jan 25, 2024 | Land Evidence Date |