Action Date | Action Description |
---|---|
Aug 09, 2023 | Maintenance Certification Request |
Aug 10, 2023 | Administrative Review for Completeness |
Aug 23, 2023 | Bio Team Review for Completeness |
Aug 23, 2023 | Application Accepted |
Aug 23, 2023 | Project Manager |
Sep 14, 2023 | HPHC Historical Preservation No Effect |
Oct 17, 2023 | Plans Received |
Oct 24, 2023 | Biologist Report |
Oct 26, 2023 | Typist for Processing |
Oct 26, 2023 | Executive Sign Off |
Oct 26, 2023 | Sent to Photo Copy |
Oct 26, 2023 | Permit Approved |
Nov 01, 2023 | Permit Mailed |