Action Date | Action Description |
---|---|
Engineering Report | |
Aug 23, 2023 | Assent Application Received |
Aug 25, 2023 | Administrative Review for Completeness |
Oct 27, 2023 | Eng Team Review for Completeness |
Oct 27, 2023 | Application Accepted |
Oct 27, 2023 | Project Manager |
Nov 29, 2023 | HPHC Historical Preservation Comments/Concerns |
Dec 19, 2023 | HPHC Historical Preservation No Effect |
May 14, 2024 | Joint Public Notice |
Jun 15, 2024 | Public Notice End Date |
Jul 15, 2024 | Public Notice End Date Extension Granted |
Aug 13, 2024 | Comments Received |
Aug 14, 2024 | Objections/Comments Received |
Aug 14, 2024 | Objections/Comments Received |
Aug 14, 2024 | Letter of Support for Project |
Aug 15, 2024 | Objections/Comments Received |
Aug 15, 2024 | Public Notice End Date Extension Granted |
Aug 20, 2024 | Objections/Comments Received |
Aug 28, 2024 | Objections/Comments Received |
Aug 28, 2024 | Objections/Comments Received |
Sep 03, 2024 | Objections/Comments Received |
Sep 03, 2024 | Objections/Comments Received |
Sep 06, 2024 | Objections/Comments Received |
Sep 12, 2024 | Objections/Comments Received |
Sep 16, 2024 | Objections/Comments Received |
Sep 19, 2024 | Objections/Comments Received |
Sep 26, 2024 | Objections/Comments Received |
Oct 28, 2024 | Additional Information Received |