Action Date | Action Description |
---|---|
Aug 25, 2023 | Assent Application Received |
Aug 30, 2023 | Administrative Review for Completeness |
Sep 08, 2023 | Bio Team Review for Completeness |
Sep 13, 2023 | Application Accepted |
Sep 13, 2023 | Project Manager |
Sep 13, 2023 | Eng Team Review for Completeness |
Oct 19, 2023 | HPHC Historical Preservation No Effect |
Oct 23, 2023 | Engineering Report |
Oct 27, 2023 | Typist for Processing |
Oct 27, 2023 | Executive Sign Off |
Oct 27, 2023 | Sent to Photo Copy |
Oct 27, 2023 | Permit Approved |
Nov 01, 2023 | Permit Mailed |