Action Date | Action Description |
---|---|
Aug 30, 2023 | Maintenance Certification Request |
Sep 08, 2023 | Administrative Review for Completeness |
Sep 08, 2023 | Bio Team Review for Completeness |
Sep 08, 2023 | Project Manager |
Sep 08, 2023 | Application Accepted |
Sep 22, 2023 | HPHC Historical Preservation No Effect |
Oct 06, 2023 | Typist for Processing |
Oct 06, 2023 | Executive Sign Off |
Oct 06, 2023 | Sent to Photo Copy |
Oct 06, 2023 | Permit Approved |
Oct 06, 2023 | Biologist Report |
Oct 12, 2023 | Permit Mailed |