Action Date | Action Description |
---|---|
Sep 05, 2023 | Assent Application Received |
Sep 12, 2023 | Administrative Review for Completeness |
Sep 13, 2023 | Bio Team Review for Completeness |
Sep 13, 2023 | Application Accepted |
Sep 13, 2023 | Project Manager |
Sep 22, 2023 | HPHC Historical Preservation No Effect |
Oct 04, 2023 | Plans Received |
Oct 30, 2023 | Plans Received |
Nov 06, 2023 | 30 day Public Notice Issued |
Dec 06, 2023 | Public Notice End Date |
Dec 13, 2023 | Plans Received |
Feb 09, 2024 | Dock/1.1.6 Review approval |
Feb 14, 2024 | Biologist Report |
Feb 19, 2024 | Typist for Processing |
Feb 19, 2024 | Executive Sign Off |
Feb 19, 2024 | Sent to Photo Copy |
Feb 19, 2024 | Permit Approved |
Feb 22, 2024 | Permit Mailed |
Mar 06, 2024 | Land Evidence Date |
Mar 19, 2024 | Commencement of Work Notice received |
Sep 17, 2024 | Dock Post-Construction Certification by Engineer received. |