Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Sep 12, 2023 | Assent Application Received |
Sep 15, 2023 | Administrative Review for Completeness |
Sep 15, 2023 | Bio Team Review for Completeness |
Sep 15, 2023 | Project Manager |
Sep 15, 2023 | Application Accepted |
Sep 15, 2023 | Category A* (Docks) |
Sep 22, 2023 | HPHC Historical Preservation No Effect |
Oct 13, 2023 | Plans Received |
Oct 23, 2023 | 30 day Public Notice Issued |
Nov 02, 2023 | Comments Received |
Nov 20, 2023 | Biologist Report |
Nov 23, 2023 | Public Notice End Date |
Nov 28, 2023 | Semi-Monthly Meeting Held |
Nov 28, 2023 | Council Approval Granted |
Nov 29, 2023 | Stipulation Package from Biologist |
Apr 15, 2024 | Typist for Processing |
Apr 15, 2024 | Executive Sign Off |
Apr 15, 2024 | Sent to Photo Copy |
Apr 18, 2024 | Permit Approved |
Apr 18, 2024 | Permit Mailed |
Apr 22, 2024 | Land Evidence Date |