Action Date | Action Description |
---|---|
Jan 03, 2024 | Assent Application Received |
Jan 08, 2024 | Administrative Review for Completeness |
Jan 09, 2024 | Bio Team Review for Completeness |
Jan 16, 2024 | Deficient Application - Owner Notification Sent |
May 16, 2024 | Deficiency Response Received |
May 22, 2024 | Bio Team Review for Completeness |
May 22, 2024 | Application Accepted |
May 22, 2024 | Project Manager |
Jun 24, 2024 | HPHC Historical Preservation No Effect |
Jul 10, 2024 | Biologist Report |
Jul 11, 2024 | Typist for Processing |
Jul 11, 2024 | Executive Sign Off |
Jul 11, 2024 | Sent to Photo Copy |
Jul 11, 2024 | Permit Approved |
Jul 16, 2024 | Permit Mailed |
Oct 08, 2024 | Land Evidence Date |