Action Date | Action Description |
---|---|
Legal Response/Decision | |
Land Evidence Date | |
Jan 18, 2024 | CHA Worksheet received |
Jan 18, 2024 | Assent Application Received |
Jan 23, 2024 | Administrative Review for Completeness |
Jan 31, 2024 | Eng Team Review for Completeness |
Jan 31, 2024 | Application Accepted |
Jan 31, 2024 | Project Manager |
Feb 06, 2024 | 30 day Public Notice Issued |
Mar 04, 2024 | Mail Agenda Notice |
Mar 05, 2024 | HPHC Historical Preservation No Effect |
Mar 05, 2024 | Supervisor Engineer SignOff |
Mar 05, 2024 | Engineering Report |
Mar 06, 2024 | Public Notice End Date |
Mar 06, 2024 | Executive Signoff of Staff Reports |
Mar 07, 2024 | Supervisor Biologist SignOff |
Mar 12, 2024 | Semi-Monthly Meeting Date Scheduled |
Mar 12, 2024 | Council Approval Granted |
Mar 22, 2024 | Plans Received |
Apr 08, 2024 | Permit Approved |
Apr 09, 2024 | Permit Mailed |
Apr 09, 2024 | Commencement of Work Notice received |