Action Date | Action Description |
---|---|
Jan 30, 2024 | Assent Application Received |
Feb 05, 2024 | Administrative Review for Completeness |
Feb 26, 2024 | Eng Team Review for Completeness |
Feb 26, 2024 | Application Accepted |
Feb 26, 2024 | Project Manager |
Mar 08, 2024 | HPHC Historical Preservation No Effect |
Mar 27, 2024 | 30 day Public Notice Issued |
Apr 27, 2024 | Public Notice End Date |
Jun 10, 2024 | US Army Corps of Engineers Approval Received |
Jul 05, 2024 | Correspondence Received |
Jul 10, 2024 | Dock/1.1.6 Review approval |
Sep 09, 2024 | Typist for Processing |
Sep 09, 2024 | Executive Sign Off |
Sep 09, 2024 | Sent to Photo Copy |
Sep 09, 2024 | Permit Approved |
Sep 09, 2024 | Engineering Report |
Sep 11, 2024 | Permit Mailed |