Action Date | Action Description |
---|---|
May 13, 2024 | Assent Application Received |
May 16, 2024 | Administrative Review for Completeness |
Jun 04, 2024 | Eng Team Review for Completeness |
Jun 04, 2024 | Project Manager |
Jun 04, 2024 | Application Accepted |
Jun 24, 2024 | HPHC Historical Preservation No Effect |
Aug 28, 2024 | Additional Information Received |
Sep 12, 2024 | Water Quality Certification |
Sep 18, 2024 | Engineering Report |
Sep 19, 2024 | Typist for Processing |
Sep 19, 2024 | Executive Sign Off |
Sep 19, 2024 | Sent to Photo Copy |
Sep 19, 2024 | Permit Approved |
Sep 23, 2024 | Permit Mailed |
Oct 08, 2024 | US Army Corps of Engineers Approval Received |