Action Date | Action Description |
---|---|
Jul 31, 2009 | Assent Application Received |
Aug 05, 2009 | Administrative Review for Completeness |
Aug 05, 2009 | Team Review for Completeness |
Aug 05, 2009 | Team Review for Completeness |
Aug 05, 2009 | Application Accepted |
Sep 01, 2009 | Biologist Report |
Sep 01, 2009 | Engineering Report |
Sep 03, 2009 | Typist for Processing |
Sep 03, 2009 | Permit Approved |
Sep 04, 2009 | Executive Sign Off |
Sep 04, 2009 | Sent to Photo Copy |
Sep 14, 2009 | Land Evidence Date |
Sep 16, 2009 | HPHC Historical Preservation No Effect |
Nov 05, 2009 | Commencement of Work Notice received |