Action Date | Action Description |
---|---|
Apr 01, 1997 | Application Accepted |
Apr 08, 1997 | Historical Preservation Approval Granted |
Oct 01, 1997 | Biologist Report |
Oct 01, 1997 | Engineering Report |
Oct 02, 1997 | Permit Approved |
Oct 02, 1997 | Land Evidence Date |
Jul 12, 2021 | Modification Request |
Jul 13, 2021 | Administrative Review for Completeness |
Jul 23, 2021 | Eng Team Review for Completeness |
Jul 23, 2021 | Project Manager |
Aug 05, 2021 | HPHC Review Pending |
Aug 05, 2021 | HPHC Historical Preservation No Effect |
Aug 24, 2021 | 30 day Public Notice Issued |
Aug 31, 2021 | Correspondence Received |
Sep 24, 2021 | Public Notice End Date |
Dec 21, 2021 | Modification Approved |
Dec 21, 2021 | Typist for Processing |
Dec 21, 2021 | Executive Sign Off |
Dec 21, 2021 | Sent to Photo Copy |
Dec 21, 2021 | Permit Mailed |
Dec 21, 2021 | Engineering Report |
Jan 24, 2022 | Land Evidence Date |