Action Date | Action Description |
---|---|
May 19, 1997 | Application Accepted |
May 23, 1997 | 30 day Public Notice Issued |
May 29, 1997 | Historical Preservation Approval Granted |
Jun 09, 1997 | Engineering Report |
Jun 16, 1997 | Biologist Report |
Jun 27, 1997 | Dock sub-committee Approved |
Jun 30, 1997 | Permit Approved |
Jun 30, 1997 | Land Evidence Date |
Feb 01, 2013 | Modification Request |
Feb 01, 2013 | Administrative Review for Completeness |
Feb 11, 2013 | Team Review for Completeness |
Feb 11, 2013 | Team Review for Completeness |
Feb 15, 2013 | HPHC Historical Preservation No Effect |
Mar 18, 2013 | Plans Received |
Apr 11, 2013 | Additional Information Received |
May 08, 2013 | Public Notice End Date |
May 14, 2013 | Correspondence Received |
May 16, 2013 | Biologist Report |
May 16, 2013 | Engineering Report |
Jun 04, 2013 | Typist for Processing |
Jun 04, 2013 | Permit Approved |
Jun 04, 2013 | Modification Approved |
Jun 06, 2013 | Executive Sign Off |
Jun 06, 2013 | Sent to Photo Copy |
Apr 09, 2018 | Modification Request |
Apr 12, 2018 | Administrative Review for Completeness |
Apr 12, 2018 | Team Review for Completeness |
Apr 12, 2018 | Application Accepted |
Apr 16, 2018 | Plans Received |
Apr 20, 2018 | HPHC Historical Preservation No Effect |
May 03, 2018 | 30 day Public Notice Issued |
Jun 03, 2018 | Public Notice End Date |
Jun 05, 2018 | Additional Information Received |
Jun 15, 2018 | Dock Meeting Scheduled (Admin) |
Jul 16, 2018 | Dock/1.1.6 Review approval |
Aug 09, 2018 | Biologist Report |
Aug 10, 2018 | Typist for Processing |
Aug 10, 2018 | Executive Sign Off |
Aug 10, 2018 | Sent to Photo Copy |
Aug 10, 2018 | Modification Approved |
Aug 27, 2018 | Land Evidence Date |