Action Date | Action Description |
---|---|
Mar 03, 2005 | Assent Application Received |
Mar 04, 2005 | Administrative Review for Completeness |
Mar 14, 2005 | Team Review for Completeness |
Mar 14, 2005 | Application Accepted |
Mar 15, 2005 | 30 day Public Notice Issued |
Mar 24, 2005 | Engineering Report |
Mar 28, 2005 | Biologist Report |
Mar 28, 2005 | Executive Sign Off |
Apr 01, 2005 | HPHC Review Pending |
Apr 01, 2005 | Historical Preservation Approval Granted |
Apr 13, 2005 | Public Notice End Date |
Apr 15, 2005 | US Army Corp of Engineers Permit Date |
Apr 18, 2005 | US Army Corps of Engineers Approval Received |
May 04, 2005 | Mail Agenda Notice |
May 10, 2005 | Semi-Monthly Meeting Held |
May 10, 2005 | Semi-Monthly Meeting Unexcused Absence |
Jun 03, 2005 | Mail Agenda Notice |
Jun 03, 2005 | Ready to Schedule Semi-Monthly Meeting |
Jun 14, 2005 | Semi-Monthly Meeting Held |
Jun 14, 2005 | Council Approval Granted |
Jun 14, 2005 | Semi-Monthly Meeting Date Scheduled |
Jun 17, 2005 | Water Quality Certification Waived |
Sep 15, 2005 | Stipulation Package by Engineer |
Sep 15, 2005 | Legal Response/Decision |
Sep 16, 2005 | Typist for Processing |
Sep 16, 2005 | Executive Sign Off |
Sep 16, 2005 | Sent to Photo Copy |
Sep 16, 2005 | Permit Approved |
Sep 21, 2005 | Stipulation Package from Biologist |