Action Date | Action Description |
---|---|
Typist for Processing | |
May 16, 2006 | Assent Application Received |
May 19, 2006 | Administrative Review for Completeness |
May 19, 2006 | Team Review for Completeness |
May 19, 2006 | Application Accepted |
May 25, 2006 | Engineering Report |
May 30, 2006 | Typist for Processing |
May 30, 2006 | Executive Sign Off |
May 30, 2006 | Sent to Photo Copy |
May 30, 2006 | Permit Approved |
Jun 01, 2006 | Land Evidence Date |
Feb 17, 2009 | Extension of Permit Request |