Action Date | Action Description |
---|---|
Aug 30, 2006 | Assent Application Received |
Aug 31, 2006 | Administrative Review for Completeness |
Sep 06, 2006 | Deficient Application - Owner Notification Sent |
Oct 16, 2006 | Deficiency Response Received |
Oct 17, 2006 | Administrative Review for Completeness |
Oct 17, 2006 | Team Review for Completeness |
Oct 17, 2006 | Application Accepted |
Nov 01, 2006 | HPHC Historical Preservation No Effect |
Nov 20, 2006 | Biologist Report |
Nov 21, 2006 | Typist for Processing |
Nov 21, 2006 | Executive Sign Off |
Nov 21, 2006 | Sent to Photo Copy |
Nov 21, 2006 | Permit Approved |
Nov 21, 2006 | Engineering Report |
Jan 04, 2007 | Land Evidence Date |
Jan 10, 2007 | Correspondence Mailed/Faxed/E-mailed |