Action Date | Action Description |
---|---|
Sep 01, 2006 | Assent Application Received |
Sep 05, 2006 | Administrative Review for Completeness |
Sep 06, 2006 | Deficient Application - Owner Notification Sent |
Sep 07, 2006 | Deficiency Response Received |
Sep 07, 2006 | Team Review for Completeness |
Sep 07, 2006 | Application Accepted |
Sep 19, 2006 | HPHC Historical Preservation No Effect |
Sep 21, 2006 | Biologist Report |
Sep 21, 2006 | Engineering Report |
Sep 22, 2006 | Typist for Processing |
Sep 22, 2006 | Executive Sign Off |
Sep 22, 2006 | Sent to Photo Copy |
Sep 22, 2006 | Permit Approved |
Oct 04, 2006 | Commencement of Work Notice received |
Oct 06, 2006 | Land Evidence Date |