Action Date | Action Description |
---|---|
Jun 27, 2007 | Assent Application Received |
Jun 27, 2007 | Administrative Review for Completeness |
Jul 03, 2007 | Team Review for Completeness |
Jul 03, 2007 | Team Review for Completeness |
Jul 03, 2007 | Application Accepted |
Jul 23, 2007 | HPHC Historical Preservation Comments/Concerns |
Aug 14, 2007 | Correspondence Received |
Aug 15, 2007 | Correspondence Received |
Nov 24, 2007 | Historical Preservation Conditional Approval |
Dec 14, 2007 | Plans Received |
Apr 16, 2008 | Plans Received |
Apr 30, 2008 | Typist for Processing |
Apr 30, 2008 | Executive Sign Off |
Apr 30, 2008 | Sent to Photo Copy |
Apr 30, 2008 | Permit Approved |
Apr 30, 2008 | Biologist Report |
Apr 30, 2008 | Engineering Report |
May 12, 2008 | Land Evidence Date |