Action Date | Action Description |
---|---|
Jul 21, 2008 | Assent Application Received |
Jul 22, 2008 | Administrative Review for Completeness |
Jul 25, 2008 | Team Review for Completeness |
Jul 25, 2008 | Team Review for Completeness |
Jul 28, 2008 | Deficient Application - Owner Notification Sent |
Aug 15, 2008 | Deficient Application Picked Up |
Oct 23, 2008 | Deficiency Response Received |
Oct 23, 2008 | Administrative Review for Completeness |
Oct 24, 2008 | Team Review for Completeness |
Oct 24, 2008 | Team Review for Completeness |
Oct 27, 2008 | Deficient Application - Owner Notification Sent |
Dec 08, 2008 | Deficiency Response Received |
Dec 22, 2008 | Additional Information Received |
Dec 24, 2008 | Team Review for Completeness |
Dec 24, 2008 | Team Review for Completeness |
Dec 24, 2008 | Application Accepted |
Dec 31, 2008 | Plans Received |
Jan 13, 2009 | Engineering Report |
Jan 13, 2009 | Biologist Report |
Jan 14, 2009 | Typist for Processing |
Jan 14, 2009 | Executive Sign Off |
Jan 14, 2009 | Sent to Photo Copy |
Jan 14, 2009 | Permit Approved |
Feb 27, 2009 | Land Evidence Date |
Mar 02, 2009 | Correspondence Received |