Action Date | Action Description |
---|---|
Sep 30, 2008 | Assent Application Received |
Oct 01, 2008 | Administrative Review for Completeness |
Oct 02, 2008 | Team Review for Completeness |
Oct 02, 2008 | Team Review for Completeness |
Oct 02, 2008 | Application Accepted |
Jan 13, 2009 | Engineering Report |
Jan 14, 2009 | Biologist Report |
Jan 15, 2009 | Executive Signoff of Staff Reports |
Apr 13, 2009 | Ready to Schedule Semi-Monthly Meeting |
Apr 13, 2009 | Mail Agenda Notice |
Apr 28, 2009 | Council Decision - Denied |
Apr 28, 2009 | Semi-Monthly Meeting Held |
Apr 28, 2009 | Semi-Monthly Meeting Date Scheduled |
May 27, 2009 | Correspondence Received |
Jun 26, 2009 | 30 Day Appeal Notification to Owner |
Jun 26, 2009 | Legal Response/Decision |
Jun 30, 2009 | Correspondence Received |
Sep 09, 2009 | Correspondence Mailed/Faxed/E-mailed |