Action Date | Action Description |
---|---|
Oct 31, 2008 | Assent Application Received |
Nov 03, 2008 | Administrative Review for Completeness |
Nov 06, 2008 | Team Review for Completeness |
Nov 06, 2008 | Team Review for Completeness |
Nov 06, 2008 | Application Accepted |
Nov 10, 2008 | Category A* (Docks) |
Nov 17, 2008 | HPHC Historical Preservation No Effect |
Nov 18, 2008 | 30 day Public Notice Issued |
Dec 18, 2008 | Public Notice End Date |
Jan 27, 2009 | Correspondence Received |
Jan 29, 2009 | Typist for Processing |
Jan 29, 2009 | Executive Sign Off |
Jan 29, 2009 | Sent to Photo Copy |
Jan 29, 2009 | Biologist Report |
Jan 29, 2009 | Engineering Report |
Jan 29, 2009 | Permit Approved |
Feb 02, 2009 | US Army Corp of Engineers Permit Date |
Feb 04, 2009 | US Army Corps of Engineers Approval Received |
Feb 17, 2009 | Land Evidence Date |