Action Date | Action Description |
---|---|
Nov 05, 2008 | Assent Application Received |
Nov 06, 2008 | Administrative Review for Completeness |
Nov 12, 2008 | Team Review for Completeness |
Nov 12, 2008 | Team Review for Completeness |
Nov 12, 2008 | Application Accepted |
Nov 12, 2008 | Category A* (Docks) |
Nov 17, 2008 | HPHC Historical Preservation No Effect |
Jan 30, 2009 | Plans Received |
Feb 26, 2009 | 30 day Public Notice Issued |
Mar 24, 2009 | Objections/Comments Received |
Mar 25, 2009 | Objections/Comments Received |
Mar 28, 2009 | Public Notice End Date |
Jun 22, 2009 | US Army Corp of Engineers Permit Date |
Jun 24, 2009 | US Army Corps of Engineers Approval Received |
Nov 30, 2009 | Biologist Report |
Nov 30, 2009 | Engineering Report |
Nov 30, 2009 | Mail Agenda Notice |
Nov 30, 2009 | Executive Signoff of Staff Reports |
Dec 08, 2009 | Council Approval Granted |
Dec 08, 2009 | Semi-Monthly Meeting Date Scheduled |
Jan 25, 2010 | Legal Response/Decision |
Jan 28, 2010 | Stipulation Package from Biologist |
Jan 28, 2010 | Stipulation Package by Engineer |
Jan 29, 2010 | Typist for Processing |
Jan 29, 2010 | Executive Sign Off |
Jan 29, 2010 | Sent to Photo Copy |
Jan 29, 2010 | Permit Approved |
May 27, 2010 | Land Evidence Date |