Action Date | Action Description |
---|---|
Nov 12, 2008 | Assent Application Received |
Nov 13, 2008 | Administrative Review for Completeness |
Nov 26, 2008 | Team Review for Completeness |
Nov 26, 2008 | Application Accepted |
Jan 05, 2009 | Engineering Report |
Jan 06, 2009 | Typist for Processing |
Jan 06, 2009 | Executive Sign Off |
Jan 06, 2009 | Sent to Photo Copy |
Jan 06, 2009 | Permit Approved |
Jan 21, 2009 | HPHC Historical Preservation No Effect |
Jan 29, 2009 | Land Evidence Date |
Jun 25, 2009 | Modification Request |
Jun 29, 2009 | Administrative Review for Completeness |
Jul 03, 2009 | Correspondence Received |
Jul 10, 2009 | Team Review for Completeness |
Jul 21, 2009 | Executive Sign Off |
Jul 21, 2009 | Modification Approved |
Jul 23, 2009 | Engineering Report |
Jul 23, 2009 | Typist for Processing |
Jul 24, 2009 | Sent to Photo Copy |
Aug 14, 2009 | Land Evidence Date |
Aug 27, 2009 | HPHC Historical Preservation No Effect |