Action Date | Action Description |
---|---|
Dec 03, 2008 | Assent Application Received |
Dec 05, 2008 | Administrative Review for Completeness |
Dec 10, 2008 | Team Review for Completeness |
Dec 10, 2008 | Team Review for Completeness |
Dec 10, 2008 | Application Accepted |
Dec 10, 2008 | Category A* (Docks) |
Dec 22, 2008 | HPHC Historical Preservation No Effect |
Mar 02, 2009 | 30 day Public Notice Issued |
Mar 24, 2009 | Objections/Comments Received |
Mar 25, 2009 | Objections/Comments Received |
Apr 02, 2009 | Public Notice End Date |
May 11, 2009 | US Army Corp of Engineers Permit Date |
May 12, 2009 | US Army Corps of Engineers Approval Received |
Aug 03, 2009 | Correspondence Received |
Nov 30, 2009 | Biologist Report |
Nov 30, 2009 | Engineering Report |
Nov 30, 2009 | Executive Signoff of Staff Reports |
Nov 30, 2009 | Stipulation Package from Biologist |
Nov 30, 2009 | Mail Agenda Notice |
Dec 01, 2009 | Stipulation Package by Engineer |
Dec 08, 2009 | Semi-Monthly Meeting Date Scheduled |
Dec 08, 2009 | Council Approval Granted |
Jan 25, 2010 | Legal Response/Decision |
Feb 08, 2010 | Permit Approved |
Feb 22, 2010 | Land Evidence Date |