Action Date | Action Description |
---|---|
Dec 09, 2008 | Assent Application Received |
Dec 10, 2008 | Administrative Review for Completeness |
Dec 10, 2008 | Team Review for Completeness |
Dec 10, 2008 | Application Accepted |
Jan 13, 2009 | Typist for Processing |
Jan 13, 2009 | Executive Sign Off |
Jan 13, 2009 | Sent to Photo Copy |
Jan 13, 2009 | Permit Approved |
Jan 13, 2009 | Engineering Report |
Jan 21, 2009 | HPHC Historical Preservation No Effect |