Dec 11, 2008 | Assent Application Received |
Dec 15, 2008 | Administrative Review for Completeness |
Mar 10, 2009 | Team Review for Completeness |
Mar 10, 2009 | Application Accepted |
Mar 23, 2009 | Biologist Report |
Mar 23, 2009 | Typist for Processing |
Mar 23, 2009 | Executive Sign Off |
Mar 23, 2009 | Sent to Photo Copy |
Mar 23, 2009 | Permit Approved |
Apr 09, 2009 | HPHC Historical Preservation No Effect |
Apr 21, 2009 | Land Evidence Date |
Nov 07, 2012 | Extension Toll letter mailed |
Feb 06, 2014 | Letter of Authorization |