Action Date | Action Description |
---|---|
Dec 12, 2008 | Assent Application Received |
Dec 15, 2008 | Administrative Review for Completeness |
Dec 29, 2008 | Team Review for Completeness |
Dec 29, 2008 | Application Accepted |
Dec 29, 2008 | Category A* (Docks) |
Jan 05, 2009 | 30 day Public Notice Issued |
Jan 27, 2009 | Plans Received |
Feb 04, 2009 | Public Notice End Date |
Feb 12, 2009 | HPHC Historical Preservation No Effect |
Feb 20, 2009 | Dock Meeting -- Approval |
Feb 23, 2009 | US Army Corp of Engineers Permit Date |
Feb 25, 2009 | US Army Corps of Engineers Approval Received |
Mar 02, 2009 | Biologist Report |
Mar 02, 2009 | Engineering Report |
Mar 03, 2009 | Typist for Processing |
Mar 03, 2009 | Executive Sign Off |
Mar 03, 2009 | Sent to Photo Copy |
Mar 03, 2009 | Permit Approved |
Mar 13, 2009 | Land Evidence Date |
May 18, 2009 | Commencement of Work Notice received |
Feb 22, 2012 | Modification Request |
Feb 23, 2012 | Administrative Review for Completeness |
Feb 27, 2012 | Team Review for Completeness |
Feb 27, 2012 | Team Review for Completeness |
Mar 09, 2012 | HPHC Historical Preservation No Effect |
Mar 19, 2012 | 30 day Public Notice Issued |
Apr 19, 2012 | Public Notice End Date |
Jun 07, 2012 | Plans Received |
Jun 08, 2012 | Biologist Report |
Jun 08, 2012 | Engineering Report |
Jun 11, 2012 | Typist for Processing |
Jun 11, 2012 | Executive Sign Off |
Jun 11, 2012 | Sent to Photo Copy |
Jun 11, 2012 | Modification Approved |
Jun 27, 2013 | Duplicate Original Assent requested/mailed |
Jul 11, 2013 | Land Evidence Date |