Action Date | Action Description |
---|---|
Dec 16, 2008 | Assent Application Received |
Dec 17, 2008 | Administrative Review for Completeness |
Dec 29, 2008 | Team Review for Completeness |
Dec 29, 2008 | Team Review for Completeness |
Dec 29, 2008 | Deficient Application - Owner Notification Sent |
Jan 23, 2009 | Deficiency Response Received |
Feb 03, 2009 | Deficient Application - Owner Notification Sent |
Feb 25, 2009 | Deficiency Response Received |
Feb 26, 2009 | Application Accepted |
Mar 04, 2009 | Biologist Report |
Mar 04, 2009 | Engineering Report |
Mar 04, 2009 | Typist for Processing |
Mar 04, 2009 | Executive Sign Off |
Mar 04, 2009 | Sent to Photo Copy |
Mar 04, 2009 | Permit Approved |
Mar 05, 2009 | HPHC Historical Preservation No Effect |
Mar 26, 2009 | Land Evidence Date |