Action Date | Action Description |
---|---|
Dec 23, 2008 | Assent Application Received |
Dec 29, 2008 | Administrative Review for Completeness |
Dec 29, 2008 | Team Review for Completeness |
Dec 29, 2008 | Team Review for Completeness |
Dec 29, 2008 | Deficient Application - Owner Notification Sent |
Jan 02, 2009 | Correspondence Received |
Jan 05, 2009 | Deficiency Response Received |
Jan 08, 2009 | Administrative Review for Completeness |
Jan 09, 2009 | Team Review for Completeness |
Jan 09, 2009 | Team Review for Completeness |
Jan 09, 2009 | Application Accepted |
Jan 12, 2009 | Engineering Report |
Jan 12, 2009 | Typist for Processing |
Jan 12, 2009 | Executive Sign Off |
Jan 12, 2009 | Sent to Photo Copy |
Jan 12, 2009 | Permit Approved |
Jan 15, 2009 | Additional Information Received |
Feb 12, 2009 | HPHC Historical Preservation No Effect |
Feb 17, 2009 | Land Evidence Date |
Feb 26, 2009 | Commencement of Work Notice received |