Action Date | Action Description |
---|---|
Jan 02, 2009 | Assent Application Received |
Jan 05, 2009 | Administrative Review for Completeness |
Jan 06, 2009 | Team Review for Completeness |
Jan 06, 2009 | Team Review for Completeness |
Jan 06, 2009 | Deficient Application - Owner Notification Sent |
Jan 21, 2009 | Deficient Application Picked Up |
Mar 20, 2009 | Biologist Report |
Mar 23, 2009 | Deficiency Response Received |
Mar 23, 2009 | Administrative Review for Completeness |
Mar 23, 2009 | Team Review for Completeness |
Mar 23, 2009 | Team Review for Completeness |
Mar 23, 2009 | Application Accepted |
Mar 24, 2009 | Engineering Report |
Mar 24, 2009 | Typist for Processing |
Mar 24, 2009 | Executive Sign Off |
Mar 24, 2009 | Sent to Photo Copy |
Mar 24, 2009 | Permit Approved |
Apr 21, 2009 | HPHC Historical Preservation No Effect |
May 20, 2009 | Commencement of Work Notice received |