Action Date |
Action Description |
Jan 21, 2009 |
Assent Application Received |
May 06, 2009 |
Aquaculture PD Letter Sent to Schedule Meeting with Town |
May 13, 2009 |
Application Accepted |
May 13, 2009 |
Category B assigned |
May 14, 2009 |
30 day Public Notice Issued |
May 20, 2009 |
Correspondence Mailed/Faxed/E-mailed |
May 21, 2009 |
HPHC Historical Preservation No Effect |
Jun 14, 2009 |
Public Notice End Date |
Jun 15, 2009 |
Plans Received |
Jun 24, 2009 |
US Army Corp of Engineers Permit Date |
Jun 26, 2009 |
US Army Corps of Engineers Approval Received |
Jul 09, 2009 |
Site Inspection |
Jul 16, 2009 |
Correspondence Received |
Jul 16, 2009 |
Correspondence Received |
Jul 17, 2009 |
Public Notice End Date Extension Granted |
Oct 06, 2009 |
DEM Fish & Wildlife Review |
Oct 07, 2009 |
Aquaculture Council Report |
Oct 14, 2009 |
Mail Agenda Notice |
Oct 14, 2009 |
Ready to Schedule Semi-Monthly Meeting |
Oct 21, 2009 |
Council Approval Granted |
Oct 21, 2009 |
Semi-Monthly Meeting Date Scheduled |
Oct 27, 2009 |
Aquaculture Lease Payment |
Oct 27, 2009 |
Permit Approved |
Oct 27, 2009 |
Typist for Processing |
Oct 27, 2009 |
Executive Sign Off |
Oct 27, 2009 |
Sent to Photo Copy |
Oct 29, 2009 |
Aquaculture Lease Mailed |
Dec 03, 2009 |
Aquaculture Lease Payment |
Jan 25, 2010 |
Legal Response/Decision |
Dec 16, 2010 |
Aquaculture Yearly Questionnaire |
Dec 16, 2010 |
Aquaculture Lease Payment |
Dec 16, 2010 |
Aquaculture Lease Received |
Mar 04, 2011 |
Modification Request |
Mar 08, 2011 |
Administrative Review for Completeness |
Mar 08, 2011 |
Team Review for Completeness |
Mar 22, 2011 |
Aquaculture Report |
Mar 22, 2011 |
Modification Approved |
Mar 23, 2011 |
HPHC Historical Preservation No Effect |
Mar 23, 2011 |
Typist for Processing |
Mar 24, 2011 |
Executive Sign Off |
Mar 24, 2011 |
Sent to Photo Copy |
Dec 28, 2011 |
Aquaculture Yearly Questionnaire |
Dec 28, 2011 |
Aquaculture Lease Payment |
Dec 31, 2012 |
Aquaculture Yearly Questionnaire |
Dec 31, 2012 |
Aquaculture Lease Payment |
Dec 31, 2012 |
Aquaculture Bond Received |
Dec 30, 2013 |
Aquaculture Yearly Questionnaire |
Dec 30, 2013 |
Aquaculture Lease Payment |
Dec 30, 2013 |
Aquaculture Bond Received |
Aug 13, 2014 |
Aquaculture Assent Renewal |
Nov 17, 2014 |
Aquaculture permit expiration reminder |
Dec 26, 2014 |
Aquaculture Lease Payment |
Jan 12, 2015 |
Aquaculture Yearly Questionnaire |
Dec 03, 2015 |
Aquaculture permit expiration reminder |
Jan 04, 2016 |
Aquaculture Lease Payment |
Jan 19, 2016 |
Aquaculture Yearly Questionnaire |
Nov 21, 2016 |
Aquaculture Lease Cover Letter sent |
Dec 27, 2016 |
Aquaculture Lease Payment |
Dec 27, 2016 |
Aquaculture Yearly Questionnaire |
Nov 01, 2017 |
Aquaculture Lease Cover Letter sent |
Dec 04, 2017 |
Aquaculture Lease Payment |
Jan 05, 2018 |
Aquaculture Yearly Questionnaire |
Dec 03, 2018 |
Aquaculture Lease Cover Letter sent |
Jan 04, 2019 |
Aquaculture Yearly Questionnaire |
Jan 04, 2019 |
Aquaculture Lease Payment |
Dec 10, 2019 |
Aquaculture Lease Cover Letter sent |
Dec 26, 2019 |
Aquaculture Lease Payment |
Jan 17, 2020 |
Correspondence Mailed/Faxed/E-mailed |
Dec 10, 2020 |
Aquaculture Bond Received |
Dec 21, 2020 |
Aquaculture Lease Cover Letter sent |
Dec 21, 2020 |
Aquaculture Lease Payment |
Jan 08, 2021 |
Aquaculture Yearly Questionnaire |
Dec 28, 2021 |
Aquaculture Lease Cover Letter sent |
Jan 05, 2022 |
Aquaculture Yearly Questionnaire |
Jan 05, 2022 |
Aquaculture Lease Payment |
Feb 09, 2022 |
Modification Request |
Feb 10, 2022 |
Administrative Review for Completeness |
Apr 12, 2022 |
Team Review for Completeness |
May 16, 2022 |
30 day Public Notice Issued |
Jun 16, 2022 |
Public Notice End Date |
Jun 21, 2022 |
Comments Received |
Sep 14, 2022 |
Additional Information Received |
Oct 13, 2022 |
Modification Approved |
Oct 13, 2022 |
Aquaculture Report |
Dec 27, 2022 |
Aquaculture Bond Received |
Dec 27, 2022 |
Aquaculture Lease Payment |
Dec 27, 2022 |
Aquaculture Yearly Questionnaire |
Dec 31, 2022 |
Aquaculture Bond Expiration |
Dec 26, 2023 |
Aquaculture Lease Payment |
Jan 04, 2024 |
Aquaculture Yearly Questionnaire |