Application 2009-02-069 Details

Back to List


Actions:

Action Date Action Description
Feb 24, 2009 Assent Application Received
Feb 25, 2009 Administrative Review for Completeness
Mar 04, 2009 Team Review for Completeness
Mar 04, 2009 Team Review for Completeness
Mar 04, 2009 Application Accepted
Oct 06, 2009 Additional Information Received
Jan 19, 2010 Additional Information Received
Feb 09, 2010 Plans Received
Feb 12, 2010 Additional Information Received
Feb 15, 2010 Biologist Report
Feb 15, 2010 Engineering Report
Feb 16, 2010 Typist for Processing
Feb 16, 2010 Executive Sign Off
Feb 16, 2010 Sent to Photo Copy
Feb 16, 2010 Permit Approved
Mar 09, 2010 Water Quality Certification
Apr 29, 2010 Correspondence Received
Aug 16, 2012 Correspondence Received
Feb 07, 2013 Extension Toll letter mailed

Details:

File No
2009-02-069
Town
Bristol
First Name
Town of Bristol
Last Name
Street
Hope Street/Tanyard Brook
Location
Hope Street/Tanyard Brook
Plat/Map
21
Lot/Block
45
Decision Date
Feb 16, 2010
Dock Reg.No
Project
Tanyard Brook-install concrete box culvert storm drains, riprap & restore vegetation
Description
Point Discharges/Drainage
Water Area
Bristol Harbor
Easement
0
Acceptance Date
Mar 04, 2009