Action Date | Action Description |
---|---|
Mar 10, 2009 | Maintenance Certification Request |
Mar 11, 2009 | Administrative Review for Completeness |
Mar 11, 2009 | Team Review for Completeness |
Mar 16, 2009 | Deficient Application - Owner Notification Sent |
May 01, 2009 | Deficient Application Picked Up |
Jun 05, 2009 | Deficiency Response Received |
Jun 09, 2009 | Administrative Review for Completeness |
Jun 10, 2009 | Team Review for Completeness |
Jun 10, 2009 | Permit Approved |
Jun 10, 2009 | Application Accepted |