Action Date | Action Description |
---|---|
Apr 02, 2009 | Assent Application Received |
Apr 04, 2009 | Administrative Review for Completeness |
Apr 06, 2009 | Team Review for Completeness |
Apr 06, 2009 | Team Review for Completeness |
Apr 06, 2009 | Application Accepted |
Apr 09, 2009 | HPHC Historical Preservation No Effect |
Apr 13, 2009 | Typist for Processing |
Apr 13, 2009 | Executive Sign Off |
Apr 13, 2009 | Sent to Photo Copy |
Apr 13, 2009 | Permit Approved |
Apr 13, 2009 | Biologist Report |
Apr 13, 2009 | Engineering Report |
Jun 30, 2009 | Water Quality Certification |