Action Date | Action Description |
---|---|
Apr 10, 2009 | Assent Application Received |
Apr 15, 2009 | Administrative Review for Completeness |
Apr 15, 2009 | Team Review for Completeness |
Apr 15, 2009 | Application Accepted |
May 20, 2009 | Engineering Report |
May 27, 2009 | HPHC Historical Preservation No Effect |
Jul 09, 2009 | Ready to Schedule Semi-Monthly Meeting |
Jul 09, 2009 | Mail Agenda Notice |
Jul 13, 2009 | Council Approval Granted |
Jul 13, 2009 | Semi-Monthly Meeting Date Scheduled |
Jul 13, 2009 | Semi-Monthly Meeting Held |
Jul 15, 2009 | Legal Response/Decision |
Jul 16, 2009 | Stipulation Package by Engineer |
Jul 16, 2009 | Typist for Processing |
Jul 16, 2009 | Executive Sign Off |
Jul 16, 2009 | Permit Approved |
Feb 25, 2010 | Modification Request |
Mar 01, 2010 | Administrative Review for Completeness |
Mar 04, 2010 | Team Review for Completeness |
Mar 04, 2010 | Engineering Report |
Mar 08, 2010 | Typist for Processing |
Mar 08, 2010 | Executive Sign Off |
Mar 08, 2010 | Sent to Photo Copy |
Mar 08, 2010 | Modification Approved |
Mar 15, 2010 | Land Evidence Date |