Action Date | Action Description |
---|---|
May 11, 2009 | Assent Application Received |
May 11, 2009 | Administrative Review for Completeness |
May 13, 2009 | Team Review for Completeness |
May 13, 2009 | Team Review for Completeness |
May 14, 2009 | Deficient Application - Owner Notification Sent |
May 21, 2009 | Deficient Application Picked Up |
Jul 22, 2009 | Deficiency Response Received |
Jul 23, 2009 | Team Review for Completeness |
Jul 23, 2009 | Application Accepted |
Aug 12, 2009 | HPHC Historical Preservation Comments/Concerns |
Aug 31, 2009 | Correspondence Received |
Dec 09, 2009 | Additional Information Received |
Dec 15, 2009 | HPHC Historical Preservation No Effect |
Feb 16, 2010 | Permit Approved |
Feb 16, 2010 | Biologist Report |
Feb 16, 2010 | Engineering Report |
Mar 09, 2010 | Land Evidence Date |
Mar 12, 2010 | Commencement of Work Notice received |