Action Date |
Action Description |
May 20, 2009 |
Assent Application Received |
May 21, 2009 |
Administrative Review for Completeness |
May 21, 2009 |
Team Review for Completeness |
May 21, 2009 |
Team Review for Completeness |
May 21, 2009 |
Application Accepted |
May 26, 2009 |
30 day Public Notice Issued |
Jun 23, 2009 |
Additional Information Received |
Jun 25, 2009 |
HPHC Historical Preservation No Effect |
Jun 26, 2009 |
Public Notice End Date |
Jul 22, 2009 |
Water Quality Certification |
Jul 31, 2009 |
Plans Received |
Sep 01, 2009 |
Biologist Report |
Sep 01, 2009 |
Engineering Report |
Sep 02, 2009 |
Supervisor Biologist SignOff |
Sep 02, 2009 |
Supervisor Engineer SignOff |
Sep 03, 2009 |
US Army Corp of Engineers Permit Date |
Sep 08, 2009 |
Executive Signoff of Staff Reports |
Sep 10, 2009 |
Ready to Schedule Semi-Monthly Meeting |
Sep 10, 2009 |
Mail Agenda Notice |
Sep 10, 2009 |
US Army Corps of Engineers Approval Received |
Sep 22, 2009 |
Semi-Monthly Meeting Date Scheduled |
Sep 22, 2009 |
Semi-Monthly Meeting Held |
Sep 22, 2009 |
Council Approval Granted |
Sep 24, 2009 |
Stipulation Package from Biologist |
Sep 24, 2009 |
Stipulation Package by Engineer |
Sep 24, 2009 |
Permit Approved |
Nov 09, 2009 |
Legal Response/Decision |
Oct 24, 2012 |
Extension Toll letter mailed |
Jan 24, 2018 |
Expiration of Assent/End of Tolling Legislation |
Mar 01, 2019 |
Extension of Permit Request |
Mar 07, 2019 |
Enforcement Compliance Inspection Required |
Mar 07, 2019 |
Process Extension |
Mar 07, 2019 |
Extension Approved |
Apr 11, 2019 |
Modification Request |
Apr 12, 2019 |
Administrative Review for Completeness |
Apr 25, 2019 |
Application Accepted |
May 16, 2019 |
Biologist Report |
May 16, 2019 |
Engineering Report |
May 16, 2019 |
Modification Approved |
May 21, 2019 |
HPHC Historical Preservation No Effect |
May 21, 2019 |
HPHC Review Pending |
May 23, 2019 |
Land Evidence Date |
May 01, 2020 |
Extension of Permit Request |
May 05, 2020 |
Enforcement Compliance Inspection Required |
May 19, 2020 |
Process Extension |
May 19, 2020 |
Extension Approved |
Mar 15, 2021 |
Extension of Permit Request |
May 11, 2021 |
Enforcement Compliance Inspection Required |
May 11, 2021 |
Extension Approved |
Jul 23, 2021 |
Commencement of Work Notice received |
May 12, 2022 |
Phone Call |
Aug 17, 2022 |
Additional Information Received |