Action Date | Action Description |
---|---|
Jul 02, 2009 | Assent Application Received |
Jul 03, 2009 | Administrative Review for Completeness |
Jul 07, 2009 | Team Review for Completeness |
Jul 07, 2009 | Team Review for Completeness |
Jul 07, 2009 | Application Accepted |
Jul 07, 2009 | 30 day Public Notice Issued |
Aug 07, 2009 | Public Notice End Date |
Aug 25, 2009 | Biologist Report |
Aug 25, 2009 | Supervisor Engineer SignOff |
Aug 26, 2009 | Engineering Report |
Aug 26, 2009 | Supervisor Biologist SignOff |
Aug 27, 2009 | HPHC Historical Preservation No Effect |
Aug 31, 2009 | Executive Signoff of Staff Reports |
Sep 02, 2009 | Ready to Schedule Semi-Monthly Meeting |
Sep 02, 2009 | Mail Agenda Notice |
Sep 08, 2009 | Council Approval Granted |
Sep 08, 2009 | Semi-Monthly Meeting Held |
Sep 08, 2009 | Semi-Monthly Meeting Date Scheduled |
Sep 08, 2009 | Category B assigned |
Sep 09, 2009 | Stipulation Package from Biologist |
Sep 09, 2009 | Stipulation Package by Engineer |
Sep 11, 2009 | Typist for Processing |
Sep 11, 2009 | Executive Sign Off |
Sep 11, 2009 | Permit Approved |
Sep 14, 2009 | Sent to Photo Copy |
Sep 17, 2009 | Land Evidence Date |
Sep 28, 2009 | US Army Corp of Engineers Permit Date |
Oct 07, 2009 | US Army Corps of Engineers Approval Received |
Oct 21, 2009 | Legal Response/Decision |