Action Date | Action Description |
---|---|
Sep 21, 2009 | Assent Application Received |
Sep 22, 2009 | Administrative Review for Completeness |
Sep 22, 2009 | Team Review for Completeness |
Sep 22, 2009 | Team Review for Completeness |
Sep 22, 2009 | Application Accepted |
Oct 20, 2009 | Additional Information Requested from Applicant |
Oct 29, 2009 | Correspondence Received |
Dec 18, 2009 | Plans Received |
Dec 28, 2009 | Biologist Report |
Dec 28, 2009 | Engineering Report |
Dec 30, 2009 | Typist for Processing |
Dec 30, 2009 | Permit Approved |
Jan 27, 2010 | Land Evidence Date |
Feb 25, 2010 | Modification Request |
Mar 01, 2010 | Administrative Review for Completeness |
Mar 01, 2010 | Team Review for Completeness |
Mar 01, 2010 | Team Review for Completeness |
Mar 11, 2010 | Engineering Report |
Mar 11, 2010 | Biologist Report |
Mar 15, 2010 | Modification Approved |
Mar 26, 2010 | HPHC Historical Preservation No Effect |
Jun 09, 2015 | Modification Request |
Jun 10, 2015 | Administrative Review for Completeness |
Jun 15, 2015 | Team Review for Completeness |
Jun 15, 2015 | Biologist Report |
Jun 15, 2015 | Typist for Processing |
Jun 15, 2015 | Modification Approved |
Jul 13, 2015 | Land Evidence Date |