Action Date | Action Description |
---|---|
Nov 25, 2011 | Assent Application Received |
Nov 25, 2011 | Administrative Review for Completeness |
Nov 28, 2011 | Team Review for Completeness |
Nov 28, 2011 | Team Review for Completeness |
Nov 28, 2011 | Application Accepted |
Jan 12, 2012 | HPHC Historical Preservation No Effect |
Mar 19, 2012 | Correspondence Received |
May 30, 2013 | Engineering Report |
Jun 05, 2013 | Typist for Processing |
Jun 05, 2013 | Permit Approved |
Jun 07, 2013 | Executive Sign Off |
Jun 07, 2013 | Sent to Photo Copy |
Jun 17, 2013 | Land Evidence Date |
Sep 04, 2013 | Commencement of Work Notice received |