Action Date | Action Description |
---|---|
Mar 27, 2012 | Maintenance Certification Request |
Mar 27, 2012 | Administrative Review for Completeness |
Mar 30, 2012 | Team Review for Completeness |
Mar 30, 2012 | Team Review for Completeness |
Mar 30, 2012 | Application Accepted |
Apr 11, 2012 | Additional Information Received |
Apr 17, 2012 | HPHC Historical Preservation No Effect |
Nov 28, 2012 | Additional Information Received |
Feb 07, 2013 | Biologist Report |
Feb 07, 2013 | Engineering Report |
Feb 12, 2013 | Typist for Processing |
Feb 12, 2013 | Permit Approved |
Feb 13, 2013 | Executive Sign Off |
Feb 13, 2013 | Sent to Photo Copy |
Mar 01, 2013 | Land Evidence Date |
Dec 11, 2018 | Permit Approved |
Apr 17, 2019 | Land Evidence Date |