Action Date | Action Description |
---|---|
Aug 17, 2012 | Preliminary Determination Request (Coastal) |
Aug 17, 2012 | Administrative Review for Completeness |
Aug 20, 2012 | Team Review for Completeness |
Aug 20, 2012 | Team Review for Completeness |
Aug 20, 2012 | Application Accepted |
Sep 07, 2012 | Additional Information Received |
Sep 12, 2012 | Typist for Processing |
Sep 12, 2012 | Biologist Report |
Sep 12, 2012 | Engineering Report |
Sep 12, 2012 | Category A assigned |
Sep 12, 2012 | HPHC Historical Preservation No Effect |
Sep 12, 2012 | Permit Approved |
Sep 14, 2012 | Executive Sign Off |
Sep 14, 2012 | Sent to Photo Copy |
Sep 20, 2012 | Assent Correction Request Received |
Sep 20, 2012 | Assent Correction Mailed |
Sep 24, 2012 | Land Evidence Date |