Action Date | Action Description |
---|---|
Sep 17, 2012 | Assent Application Received |
Sep 17, 2012 | Administrative Review for Completeness |
Sep 18, 2012 | Team Review for Completeness |
Sep 18, 2012 | Team Review for Completeness |
Sep 18, 2012 | Application Accepted |
Sep 27, 2012 | HPHC Historical Preservation No Effect |
Nov 20, 2012 | Additional Information Received |
Dec 03, 2012 | Additional Information Received |
Jan 09, 2013 | Additional Information Received |
Jan 10, 2013 | Water Quality Certification |
Jan 10, 2013 | Water Quality Certification |
Jan 29, 2013 | Biologist Report |
Jan 29, 2013 | Engineering Report |
Jan 30, 2013 | Typist for Processing |
Jan 30, 2013 | Executive Sign Off |
Jan 30, 2013 | Permit Approved |
Jan 31, 2013 | Sent to Photo Copy |
Mar 08, 2013 | Land Evidence Date |
Jan 16, 2014 | Modification Request |
Jan 17, 2014 | Administrative Review for Completeness |
Jan 23, 2014 | Application Accepted |
Jan 28, 2014 | Team Review for Completeness |
Jan 28, 2014 | Team Review for Completeness |
Feb 17, 2014 | Engineering Report |
Feb 18, 2014 | Typist for Processing |
Feb 18, 2014 | Modification Approved |
Feb 19, 2014 | Executive Sign Off |
Feb 19, 2014 | Sent to Photo Copy |
Feb 24, 2014 | Land Evidence Date |
Feb 25, 2014 | HPHC Historical Preservation No Effect |
Apr 09, 2014 | Commencement of Work Notice received |