Action Date | Action Description |
---|---|
Feb 06, 2014 | Assent Application Received |
Feb 07, 2014 | Administrative Review for Completeness |
Feb 21, 2014 | Team Review for Completeness |
Feb 21, 2014 | Application Accepted |
Feb 26, 2014 | Biologist Report |
Feb 28, 2014 | Typist for Processing |
Feb 28, 2014 | Executive Sign Off |
Feb 28, 2014 | Sent to Photo Copy |
Feb 28, 2014 | Permit Approved |
Mar 04, 2014 | HPHC Historical Preservation No Effect |
Mar 24, 2014 | Land Evidence Date |
Mar 26, 2014 | Plans Received |
Mar 27, 2014 | Typist for Processing |
Mar 27, 2014 | Assent Amended |
Mar 28, 2014 | Executive Sign Off |
Mar 28, 2014 | Sent to Photo Copy |
Apr 14, 2014 | Land Evidence Date |