Action Date | Action Description |
---|---|
HPHC Historical Preservation No Effect | |
Apr 07, 2015 | Assent Application Received |
Apr 13, 2015 | Administrative Review for Completeness |
Apr 14, 2015 | Team Review for Completeness |
Apr 14, 2015 | Application Accepted |
Apr 14, 2015 | Engineering Report |
May 22, 2015 | Plans Received |
Jun 08, 2015 | Typist for Processing |
Jun 08, 2015 | Permit Approved |
Jun 10, 2015 | Executive Sign Off |
Jun 10, 2015 | Sent to Photo Copy |
Jun 22, 2015 | Land Evidence Date |
Mar 30, 2016 | Modification Request |
Mar 30, 2016 | Administrative Review for Completeness |
Apr 08, 2016 | Team Review for Completeness |
Apr 08, 2016 | Deficient Application - Owner Notification Sent |
Apr 19, 2016 | Deficiency Response Received |
Apr 22, 2016 | Typist for Processing |
Apr 22, 2016 | Modification Approved |
Apr 25, 2016 | Executive Sign Off |
Apr 25, 2016 | Sent to Photo Copy |
May 04, 2016 | Land Evidence Date |
Sep 02, 2016 | Commencement of Work Notice received |