Sep 22, 2015 | Assent Application Received |
Sep 23, 2015 | Administrative Review for Completeness |
Oct 07, 2015 | Team Review for Completeness |
Oct 07, 2015 | Deficient Application - Owner Notification Sent |
Oct 07, 2015 | Deficient Application Picked Up |
Oct 21, 2015 | Deficiency Response Received |
Oct 29, 2015 | Team Review for Completeness |
Oct 29, 2015 | Application Accepted |
Oct 29, 2015 | Biologist Report |
Nov 03, 2015 | Typist for Processing |
Nov 03, 2015 | Executive Sign Off |
Nov 03, 2015 | Sent to Photo Copy |
Nov 03, 2015 | Permit Approved |
Nov 10, 2015 | HPHC Historical Preservation No Effect |
Feb 18, 2016 | Land Evidence Date |