Action Date | Action Description |
---|---|
Oct 16, 2015 | Assent Application Received |
Oct 19, 2015 | Administrative Review for Completeness |
Oct 29, 2015 | Team Review for Completeness |
Oct 29, 2015 | Deficient Application - Owner Notification Sent |
Nov 03, 2015 | Deficient Application Picked Up |
May 10, 2016 | Deficiency Response Received |
May 13, 2016 | Team Review for Completeness |
May 13, 2016 | Deficient Application - Owner Notification Sent |
Aug 23, 2016 | Deficiency Response Received |
Aug 24, 2016 | Team Review for Completeness |
Aug 24, 2016 | Application Accepted |
Aug 24, 2016 | Biologist Report |
Sep 07, 2016 | HPHC Historical Preservation No Effect |
Sep 08, 2016 | Typist for Processing |
Sep 12, 2016 | Executive Sign Off |
Sep 12, 2016 | Sent to Photo Copy |
Sep 12, 2016 | Permit Approved |
Oct 20, 2016 | Land Evidence Date |