Action Date | Action Description |
---|---|
Feb 29, 2016 | Assent Application Received |
Mar 01, 2016 | Administrative Review for Completeness |
Mar 03, 2016 | Team Review for Completeness |
Mar 03, 2016 | Team Review for Completeness |
Mar 03, 2016 | Application Accepted |
Mar 07, 2016 | 30 day Public Notice Issued |
Mar 08, 2016 | HPHC Historical Preservation No Effect |
Mar 08, 2016 | Mail Agenda Notice |
Mar 08, 2016 | Public Hearing Notices Mailed |
Mar 24, 2016 | Plans Received |
Mar 24, 2016 | Correspondence Received |
Mar 25, 2016 | Objections/Comments Received |
Apr 07, 2016 | Executive Signoff of Staff Reports |
Apr 07, 2016 | Engineering Report |
Apr 07, 2016 | Biologist Report |
Apr 08, 2016 | Public Notice End Date |
Apr 11, 2016 | Continued Application by the Council |
Apr 11, 2016 | Mail Agenda Notice |
Apr 12, 2016 | Semi-Monthly Meeting Date Scheduled |
Apr 26, 2016 | Semi-Monthly Meeting Date Scheduled |
May 03, 2016 | Legal Response/Decision |
May 12, 2016 | Category B assigned |
May 13, 2016 | Typist for Processing |
May 13, 2016 | Executive Sign Off |
May 13, 2016 | Sent to Photo Copy |
May 13, 2016 | Permit Approved |
May 20, 2016 | Land Evidence Date |
Sep 29, 2017 | Plans Received |
Oct 10, 2017 | Modification Request |
Oct 10, 2017 | Administrative Review for Completeness |
Oct 11, 2017 | Team Review for Completeness |
Oct 11, 2017 | Application Accepted |
Oct 13, 2017 | Comments Received |
Nov 08, 2017 | Plans Received |
Nov 28, 2017 | HPHC Historical Preservation No Effect |
Dec 07, 2017 | Plans Received |
Dec 18, 2017 | Modification Approved |
Dec 18, 2017 | Biologist Report |
Dec 18, 2017 | Permit Approved |
Dec 29, 2017 | Land Evidence Date |