Action Date | Action Description |
---|---|
Mar 29, 2019 | Team Review for Completeness |
Mar 29, 2019 | Application Accepted |
Mar 29, 2019 | Assent Application Received |
Mar 29, 2019 | Administrative Review for Completeness |
Apr 22, 2019 | HPHC Review Pending |
Apr 22, 2019 | HPHC Historical Preservation No Effect |
May 13, 2019 | Plans Received |
Jun 05, 2019 | Biologist Report |
Jun 06, 2019 | Typist for Processing |
Jun 06, 2019 | Executive Sign Off |
Jun 06, 2019 | Sent to Photo Copy |
Jun 06, 2019 | Permit Approved |
Jun 21, 2019 | Land Evidence Date |
Sep 09, 2021 | Modification Request |
Sep 10, 2021 | Administrative Review for Completeness |
Sep 17, 2021 | Bio Team Review for Completeness |
Sep 20, 2021 | Project Manager |
Oct 05, 2021 | Plans Received |
Oct 06, 2021 | Stipulation Package from Biologist |
Oct 06, 2021 | Biologist Report |
Oct 27, 2021 | HPHC Review Pending |
Oct 27, 2021 | HPHC Historical Preservation No Effect |
Oct 29, 2021 | Typist for Processing |
Oct 29, 2021 | Modification Approved |
Nov 12, 2021 | Land Evidence Date |